Outlook Elementary School
Restoration
3800 Van
Bell Road
Outlook,
WA
Project Description
A fire
occurred at Outlook Elementary just before Christmas and resulted in the
complete loss of the cafeteria, commons and stage areas of the building
along with substantial smoke and water damage throughout the entire
building. Chervenell mobilized resources to the site the very next day
and was able to facilitate an impressive cleanup and restoration effort
which resulted in the school being allowed to resume classes as
scheduled after their winter vacation. The fourth grade wing was one of
the most heavily damaged areas and required the removal of sheet rock,
fixtures, cabinets and ceilings. This wing was put back into use less
then two months after the fire.
Chervenell is now
engaged in the construction of the new commons building and classroom as
well as the new upgraded kitchen. This work is scheduled for completion
in January 2008 at which time the school will be back to full operating
capacity.

|